Construction Sequence

The list below shows the basic construction sequence. It is up to the individual builder to decide when to make individual componetnts such as the rudder or centreboard case.

  • Prepare Hull Panels
  • Set up Jig and secure to floor
  • Fix fore and aft bulkheads to the jig
  • Fit Hull panels to the jig, cable tie seams
  • Tape outer seams and fair
  • Attach Skeg
  • Fill and fair seams
  • Flow coat and prime hull
  • Remove hull from jig
  • Fit forward longitudinal frame
  • Fit half bulkheads forward
  • Fit aft longitudinal bulkhead and transom doubler
  • Fit centrecase
  • Fit side tank bulkheads
  • Fit side tank side panels
  • Fillet and tape joints
  • Fit battens to bulkhead and frame upper edges.
  • Fit deck
  • Fit gunwhale/inwhale
  • Fit quarter knees